RFD and RFI linac system can be provided, tailored to your specific requirements, through a Development Contract. This contract will require a schedule of progress payments as outlined below:
First Installment - 30% of
Contract Amount on initiation of Contract, covers
Completion of all design documents,
Critical Design Review,
Initiation of fabrication of all major components.
Second Installment - 30% of Contract Amount when all
major components are in fabrication, covers
Completion of fabrication of all major components,
Procurement of some commercial equipment systems,
Specification and procurement of computer control system.
Third Installment - 20% of
Contract Amount on start of Commissioning, covers
Final Assembly,
Systems Integration,
Commissioning.
Fourth Installment - 20% of Contract
Amount on acceptance by customer, covers
Transfer and setup at customer's site,
Instructional manuals,
Basic operator training.
.
|